6 boilers – each 220 tons per hour @ 120 bar & superheated to 520°C + 2 x 117 MW turbines
6 x 240 ton per hour boilers @ 120 bar and 525°C + 4 x 28 MW turbines + 1 x 29 MW turbine + 1 x 36,5 MW turbine
3 waste heat boilers 15-38 tons per hour @ 40 bar etc…